Scope and what it costs
Fixr’s 2026 cost guide gives a national average of $12,000 for a bathroom remodel and a typical range of $6,000 to $18,000. By scope:
- Minor update ($2,400–$10,000): paint, lighting, faucet, vanity top, accessories.
- Partial remodel ($6,000–$25,000): several major elements replaced in the same layout.
- Full gut renovation ($9,000–$30,000 or more): everything out to the studs.
Labor is about half the cost. A small bathroom still needs a plumber, an electrician, and a tile setter, which is why price does not shrink in proportion to size. The Bathroom Remodel Cost Estimator narrows these ranges by bathroom type.
Layout: leave the drains alone if you can
Moving a toilet or shower drain means opening the floor and re-running drain and vent pipes. On a concrete slab, it means cutting concrete. Replacing fixtures in their existing positions is far simpler. If the layout must change, moving a vanity is usually easier than moving a toilet.
The parts you won’t see
Waterproofing
Tile and grout are not waterproof. What protects the wall and floor is the waterproofing system behind them: a membrane or board system installed to the manufacturer’s instructions, with a properly sloped shower floor. Ask your contractor which system they use and how they test it before tiling. This is the last place to save money.
Ventilation
An exhaust fan ducted to the outdoors — not into the attic — removes moisture that otherwise feeds mold and peels paint. Size the fan for the room and put it on a timer or humidity control.
Electrical
Bathroom outlets need ground-fault protection, and older bathrooms often lack a dedicated circuit. Heated floors, towel warmers, and lighted mirrors each add electrical needs, so decide on them before rough-in.
Choices that drive the budget
- Shower or tub. A prefabricated unit is the least expensive. A custom tiled shower with glass is the most.
- Tile. Price varies enormously by material, and labor rises with small mosaics, large-format tile, and patterns. Size the order with the Tile Calculator.
- Vanity. Stock sizes cost much less than custom.
- Fixtures. Faucets and valves range widely; the valve inside the wall matters more than the trim you see.
List each line and total it with the Bathroom Remodel Planner.
Order of work
- Demolition
- Framing changes and any subfloor repair
- Rough plumbing and electrical, then inspection where required
- Insulation, backer board, and waterproofing
- Tile and grout
- Paint
- Vanity, countertop, toilet, fixtures, glass, and accessories
Each step waits on the one before, so have all materials on site before demolition. Custom shower glass is measured after tile is finished and can add a wait at the end.
Plan for surprises
Water damage behind old tile, undersized or corroded pipes, and wiring that does not meet current code are common finds. Hold a contingency of at least 10%, more in older homes.
Permits
Plumbing and electrical changes usually need permits. Fixr reports permits average about $500. Check with your local building department before work starts.
If this is your only bathroom
Ask the contractor how long the toilet and shower will be out of service and plan around it. Having every material on site before work begins is the best way to shorten that period.
Source for cost figures: Fixr, “Bathroom Remodeling Cost,” updated January 27, 2026.
Reviewed October 2026. Figures are national planning numbers, not quotes. Methodology